Oura Water Treatment Plant - Stage 3, Pump Station and Dosing Building
Overview
Goldenfields Water engaged Van Mal Group Construction Pty Ltd in August 2024 to undertake the design and construction of a new pump station and dosing building at the Oura Water Treatment Plant. On its own, the pump station and dosing building upgrade contract is valued at $6.3M and forms part of the greater stage 3 of the Oura Water Treatment Plant Upgrade, which in total is valued at approximately $10.7M.
Overall, stage 3 of the upgrade includes:
- Design and construction of new pump station and dosing buildings, as well as their associated services, including electrical, HVAC and drainage.
- Procurement of all pipework, fittings and ancillaries, and the construction of new pipeline sections connecting the new buildings to existing Goldenfields Water infrastructure.
- Site civil and roadworks, including stormwater infrastructure.
- Demolition of redundant Goldenfields Water assets; the existing Oura reservoir and dosing buildings.
- Commissioning of 3 new pumps and high voltage motors.
- Installation and commissioning of new chlorine and fluoride dosing equipment.
Project Progress
- Designs were developed over the last few months of 2024 and completed in early 2025.
- Site mobilisation was completed in early 2025, with bulk earthworks and site preparation being completed in January.
- 200m of pump station discharge pipeline was constructed and completed in February and March 2025.
- Dosing building slab was prepared and poured in March 2025, including building services preparation and connection. Blockwork wall construction to follow suit.
- Pump station building slab preparation currently underway, with concrete being poured in early April 2025. Individual slabs for each of the 3 new pumps and motors were poured in March 2025.
- Existing Oura reservoir demolition to be completed in May 2025.
- Building and pipeline construction to be completed in November 2025.
- New dosing building to be fitted out with chlorine and fluoride dosing equipment and commissioned in late 2025 (separate contracts).
- New pumps to be installed and commissioned TBC.
Dosing building before concrete pour.
Dosing building after concrete pour.
Project Benefits
- Replace ageing building infrastructure that is showing signs of failure.
- Increase pumping capacity to meet future population growth and water demands, with variable speed drives for improved efficiency.
- Replace end-of-life dosing equipment with new equipment sized to meet future water demands.
Pump station building slab preparations.
200m of discharge pipeline being laid.