Oura Water Treatment Plant - Stage 2, Reservoir & Aerator Construction
Overview
Goldenfields Water have engaged Quay Civil Pty Ltd to undertake the $12.6 million detailed design and construction of new water infrastructure at the Oura Water Treatment Plant.
The design and construction of the reservoirs and aerators forms Stage 2 of the Oura Water Treatment Plant Upgrade.
Works for Stage 2 will include:
- the finalisation of the preliminary designs for the construction of the proposed multi tray aeration unit and structural tower
- transfer pipeline
- two reservoirs (4ML each)
- associated civil and electrical infrastructure along with instrumentation for the operation and monitoring of the system
Above: an original reservoir at the Oura Water Treatment Plant site
Timing
- Site mobilisation was completed mid-September 2023.
- The base of the two reservoirs were poured in January/February 2024.
- The DN750 stainless steel inlet and outlet pipes that the GWCC Mechanical team fabricated specifically for the project have been installed.
- A total of 48 individual concrete panels make up the walls of the reservoirs. Each panel was poured individually then lifted into place via a crane over several months, before a specialised type of concrete was poured between each panel to connect them. This process was completed in May 2024.
- Hydrostatic testing of the tanks was completed successfully in March 2025.
- Aeration units were assembled and lifted onto their supporting structural tower in March 2025. Connecting pipework is to be installed and hydrostatically tested in April 2025.
- Final civil and earthworks are to be completed in April 2025, including surface water drainage and road construction.
- Roofing for the tanks is to be installed in May 2025, marking the full completion of the project and stage 2 of the Oura Water Treatment Plant Upgrade.

Above: GWCC Chairperson Matt Stadtmiller, General Manager Aaron Drenovski, Production and Services Manager Geoff Veneris alongside Quay Civil Pty Ltd representatives on site early October 2023.
Above: One of the DN750 stainless steel pipes the Mechanical team fabricated in our Temora workshop
Above: aerial view of excavation works, preparing for the new reservoirs.
Above: 3am start for the contractors pouring the second reservoir base slab
Above: Sunrise on slab pour day
Above: Aerial view of both reservoir bases
Project Benefits
- Increased water storage capacity for growth in towns supplied from our Oura Scheme
- Reduced potential for disruption to supply when maintenance works are carried out on reservoirs
- Increased treatment time to improve water quality
Above: Reservoirs after construction.
More Information
For more information on this project, call the Goldenfields Water office on 6977 3200 between 9am and 4.30pm, Monday to Friday.